PROJECT UPDATE

Poseidon Customer – Blue Iron Foundations & Shoring LLC

Project Name – South San Francisco Shoreline Reaches 1 and 2/3

Owner – U.S. Army Corps of Engineers

Project Description – Installation of approx. 4,600LF of sheet pile cofferdam to facilitate existing levee degrade and reconstruction. All work was performed using Blue Iron’s vibro equipped Hitachi Excavator working atop Poseidon P2-5′ barges. Retained water height varied throughout up to a maximum of 16′ and utilized sheet pile lengths up to 45′ in length.